ID |
Task_Name |
Duration |
Start_Date |
Finish_Date |
Predecessors |
Resource_Names |
1 |
Preparation
- server install, project planning |
20 days |
Mon 9/2/02 |
Fri 9/27/02 |
|
|
2 |
Phase 1 -
Test and Design |
65 days? |
Mon 9/23/02 |
Fri 12/20/02 |
|
|
3 |
Basic monitoring
- replacing current functionality |
65 days? |
Mon 9/23/02 |
Fri 12/20/02 |
|
|
4 |
Setup Radegast
on platform |
6 days? |
Mon 9/23/02 |
Mon 9/30/02 |
|
Eric |
5 |
Install ORACLE |
2 days? |
Mon 9/30/02 |
Tue 10/1/02 |
|
Dave |
6 |
Install NNM |
1.33 days? |
Tue 10/1/02 |
Wed 10/2/02 |
|
Paul,Bill,Klara |
7 |
Install OVO |
1 day? |
Thu 10/3/02 |
Thu 10/3/02 |
|
Paul,Klara |
8 |
Install clients
on test hardware - AIX, SUN, Linux, Windows, (Mainframe?)
|
15 days |
Fri 10/4/02 |
Thu 10/24/02 |
7 |
Bob,Eric,Klara,Dale |
9 |
Install SNMP
monitors (for example: http://net-snmp.sourceforge.net) |
15 days |
Fri 10/4/02 |
Thu 10/24/02 |
7 |
Bob,Eric,Klara,Paul |
10 |
Compare SNMP
and OpenView monitors |
7.5 days |
Fri 10/25/02 |
Tue 11/5/02 |
9 |
Bob,Eric,Klara,Dale |
11 |
Security |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
Kim,Paul,Bob,Eric,Klara |
12 |
Evaluate BEA
Welogic App Server SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Klara,Pam Stagl,Mike Ates |
13 |
Evaluate BEA
Welogic Web Server SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Klara,Pam Stagl,Mike Ates |
14 |
Evaluate BEA
Tuxedo SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Klara ?? |
15 |
EvalutatePeopleSoft
SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Klara ?? |
16 |
Evaluate ORACLE
SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Dave Rhude |
17 |
Evaluate iPlanet
SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Klara ?? |
18 |
Evaluate Portal
Infranet SPI |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Paul,Klara |
19 |
Evaluate Internet
services |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Mike Ates,Pam Stagl,Klara |
20 |
Mainfarme monitoring |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Steve Wilcox |
21 |
Telecom monitoring |
20 days |
Thu 10/31/02 |
Wed 11/27/02 |
|
Klara,Catie Isenberg,Terri Kopish |
22 |
Map building
and event correlation |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
Paul,Bill,Scott |
23 |
Design implementation
method for server hardware monitoring with timeline |
15 days |
Mon 12/2/02 |
Fri 12/20/02 |
22 |
everyone |
24 |
Service monitoring
- correlating events to provide a single service view.
Evaluate use of SPIs |
61 days |
Mon 9/30/02 |
Mon 12/23/02 |
|
|
25 |
Design monitoring
solution for critical Applications |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
26 |
Hospital |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
27 |
HAN/NEDSS |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
28 |
911 Database
and data transfer |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
29 |
DoIT Telemanagement |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
30 |
DoIT Directory
and Messaging |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
31 |
ISIS |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
32 |
MUM |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
33 |
WiscMail |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
34 |
SFS |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
35 |
FASTAR |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
36 |
WEBCT |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
37 |
Library |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
38 |
Housing |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
39 |
APBS |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
40 |
HR |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
41 |
ESIS |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
42 |
Legacy Accounting |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
43 |
Tax Reporting |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
44 |
Purchase Order
Print |
20 days |
Wed 11/20/02 |
Tue 12/17/02 |
|
|
45 |
Map building
and event correlation |
35 days |
Thu 10/31/02 |
Wed 12/18/02 |
|
|
46 |
Security |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
47 |
Design timeline
for implementation service by service addressing mission
critical services first. Mission critical services
have been identified in the DRP document. (summarize
individual documents) |
5 days |
Tue 12/17/02 |
Mon 12/23/02 |
|
|
48 |
Network |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
49 |
Use test network
(21st Ctry network) to test device monitoring |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
50 |
Use WiscNET
to test autodiscovery |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
51 |
Map building
and event correlation |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
52 |
Security |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
53 |
Design timeline
for implementation of monitoring both the new platfrom
network and the 21st Ctry network |
45 days |
Mon 9/30/02 |
Fri 11/29/02 |
|
|
54 |
Nontechnical |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
55 |
QoS |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
56 |
Procedures
for problem resolution |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
57 |
Problem ownership |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
58 |
What does HD
do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
59 |
What does DCO
do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
60 |
What does NET
do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
61 |
What do SEO
technologists do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
62 |
What does NET
do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
63 |
What do ADI
do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
64 |
What does EIS
do? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
65 |
Ongoing role
for Security group? |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
66 |
Bringing up
additional/new devices/services |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
67 |
Intergration
with Clarify |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|
68 |
Hosting of
external customers |
50 days |
Mon 9/30/02 |
Fri 12/6/02 |
|
|