ID
Task_Name
Duration Start_Date Finish_Date Predecessors Resource_Names
1
Preparation - server install, project planning
20 days Mon 9/2/02 Fri 9/27/02    
2
Phase 1 - Test and Design
65 days? Mon 9/23/02 Fri 12/20/02    
3
Basic monitoring - replacing current functionality
65 days? Mon 9/23/02 Fri 12/20/02    
4
Setup Radegast on platform
6 days? Mon 9/23/02 Mon 9/30/02   Eric
5
Install ORACLE
2 days? Mon 9/30/02 Tue 10/1/02   Dave
6
Install NNM
1.33 days? Tue 10/1/02 Wed 10/2/02   Paul,Bill,Klara
7
Install OVO
1 day? Thu 10/3/02 Thu 10/3/02   Paul,Klara
8
Install clients on test hardware - AIX, SUN, Linux, Windows, (Mainframe?)
15 days Fri 10/4/02 Thu 10/24/02 7 Bob,Eric,Klara,Dale
9
Install SNMP monitors (for example: http://net-snmp.sourceforge.net)
15 days Fri 10/4/02 Thu 10/24/02 7 Bob,Eric,Klara,Paul
10
Compare SNMP and OpenView monitors
7.5 days Fri 10/25/02 Tue 11/5/02 9 Bob,Eric,Klara,Dale
11
Security
45 days Mon 9/30/02 Fri 11/29/02   Kim,Paul,Bob,Eric,Klara
12
Evaluate BEA Welogic App Server SPI
20 days Thu 10/31/02 Wed 11/27/02   Klara,Pam Stagl,Mike Ates
13
Evaluate BEA Welogic Web Server SPI
20 days Thu 10/31/02 Wed 11/27/02   Klara,Pam Stagl,Mike Ates
14
Evaluate BEA Tuxedo SPI
20 days Thu 10/31/02 Wed 11/27/02   Klara ??
15
EvalutatePeopleSoft SPI
20 days Thu 10/31/02 Wed 11/27/02   Klara ??
16
Evaluate ORACLE SPI
20 days Thu 10/31/02 Wed 11/27/02   Dave Rhude
17
Evaluate iPlanet SPI
20 days Thu 10/31/02 Wed 11/27/02   Klara ??
18
Evaluate Portal Infranet SPI
20 days Thu 10/31/02 Wed 11/27/02   Paul,Klara
19
Evaluate Internet services
20 days Thu 10/31/02 Wed 11/27/02   Mike Ates,Pam Stagl,Klara
20
Mainfarme monitoring
20 days Thu 10/31/02 Wed 11/27/02   Steve Wilcox
21
Telecom monitoring
20 days Thu 10/31/02 Wed 11/27/02   Klara,Catie Isenberg,Terri Kopish
22
Map building and event correlation
45 days Mon 9/30/02 Fri 11/29/02   Paul,Bill,Scott
23
Design implementation method for server hardware monitoring with timeline
15 days Mon 12/2/02 Fri 12/20/02 22 everyone
24
Service monitoring - correlating events to provide a single service view. Evaluate use of SPIs
61 days Mon 9/30/02 Mon 12/23/02    
25
Design monitoring solution for critical Applications
20 days Wed 11/20/02 Tue 12/17/02    
26
Hospital
20 days Wed 11/20/02 Tue 12/17/02    
27
HAN/NEDSS
20 days Wed 11/20/02 Tue 12/17/02    
28
911 Database and data transfer
20 days Wed 11/20/02 Tue 12/17/02    
29
DoIT Telemanagement
20 days Wed 11/20/02 Tue 12/17/02    
30
DoIT Directory and Messaging
20 days Wed 11/20/02 Tue 12/17/02    
31
ISIS
20 days Wed 11/20/02 Tue 12/17/02    
32
MUM
20 days Wed 11/20/02 Tue 12/17/02    
33
WiscMail
20 days Wed 11/20/02 Tue 12/17/02    
34
SFS
20 days Wed 11/20/02 Tue 12/17/02    
35
FASTAR
20 days Wed 11/20/02 Tue 12/17/02    
36
WEBCT
20 days Wed 11/20/02 Tue 12/17/02    
37
Library
20 days Wed 11/20/02 Tue 12/17/02    
38
Housing
20 days Wed 11/20/02 Tue 12/17/02    
39
APBS
20 days Wed 11/20/02 Tue 12/17/02    
40
HR
20 days Wed 11/20/02 Tue 12/17/02    
41
ESIS
20 days Wed 11/20/02 Tue 12/17/02    
42
Legacy Accounting
20 days Wed 11/20/02 Tue 12/17/02    
43
Tax Reporting
20 days Wed 11/20/02 Tue 12/17/02    
44
Purchase Order Print
20 days Wed 11/20/02 Tue 12/17/02    
45
Map building and event correlation
35 days Thu 10/31/02 Wed 12/18/02    
46
Security
45 days Mon 9/30/02 Fri 11/29/02    
47
Design timeline for implementation service by service addressing mission critical services first. Mission critical services have been identified in the DRP document. (summarize individual documents)
5 days Tue 12/17/02 Mon 12/23/02    
48
Network
45 days Mon 9/30/02 Fri 11/29/02    
49
Use test network (21st Ctry network) to test device monitoring
45 days Mon 9/30/02 Fri 11/29/02    
50
Use WiscNET to test autodiscovery
45 days Mon 9/30/02 Fri 11/29/02    
51
Map building and event correlation
45 days Mon 9/30/02 Fri 11/29/02    
52
Security
45 days Mon 9/30/02 Fri 11/29/02    
53
Design timeline for implementation of monitoring both the new platfrom network and the 21st Ctry network
45 days Mon 9/30/02 Fri 11/29/02    
54
Nontechnical
50 days Mon 9/30/02 Fri 12/6/02    
55
QoS
50 days Mon 9/30/02 Fri 12/6/02    
56
Procedures for problem resolution
50 days Mon 9/30/02 Fri 12/6/02    
57
Problem ownership
50 days Mon 9/30/02 Fri 12/6/02    
58
What does HD do?
50 days Mon 9/30/02 Fri 12/6/02    
59
What does DCO do?
50 days Mon 9/30/02 Fri 12/6/02    
60
What does NET do?
50 days Mon 9/30/02 Fri 12/6/02    
61
What do SEO technologists do?
50 days Mon 9/30/02 Fri 12/6/02    
62
What does NET do?
50 days Mon 9/30/02 Fri 12/6/02    
63
What do ADI do?
50 days Mon 9/30/02 Fri 12/6/02    
64
What does EIS do?
50 days Mon 9/30/02 Fri 12/6/02    
65
Ongoing role for Security group?
50 days Mon 9/30/02 Fri 12/6/02    
66
Bringing up additional/new devices/services
50 days Mon 9/30/02 Fri 12/6/02    
67
Intergration with Clarify
50 days Mon 9/30/02 Fri 12/6/02    
68
Hosting of external customers
50 days Mon 9/30/02 Fri 12/6/02    

 

 