| ID | 
                        Task_Name  | 
                        Duration | 
                        Start_Date | 
                        Finish_Date | 
                        Predecessors | 
                        Resource_Names | 
                      
                      
                        | 1 | 
                        Preparation 
                            - server install, project planning  | 
                        20 days | 
                        Mon 9/2/02 | 
                        Fri 9/27/02 | 
                          | 
                          | 
                      
                      
                        | 2 | 
                        Phase 1 - 
                            Test and Design  | 
                        65 days? | 
                        Mon 9/23/02 | 
                        Fri 12/20/02 | 
                          | 
                          | 
                      
                      
                        | 3 | 
                        Basic monitoring 
                            - replacing current functionality  | 
                        65 days? | 
                        Mon 9/23/02 | 
                        Fri 12/20/02 | 
                          | 
                          | 
                      
                      
                        | 4 | 
                        Setup Radegast 
                            on platform  | 
                        6 days? | 
                        Mon 9/23/02 | 
                        Mon 9/30/02 | 
                          | 
                        Eric | 
                      
                      
                        | 5 | 
                        Install ORACLE  | 
                        2 days? | 
                        Mon 9/30/02 | 
                        Tue 10/1/02 | 
                          | 
                        Dave | 
                      
                      
                        | 6 | 
                        Install NNM  | 
                        1.33 days? | 
                        Tue 10/1/02 | 
                        Wed 10/2/02 | 
                          | 
                        Paul,Bill,Klara | 
                      
                      
                        | 7 | 
                        Install OVO  | 
                        1 day? | 
                        Thu 10/3/02 | 
                        Thu 10/3/02 | 
                          | 
                        Paul,Klara | 
                      
                      
                        | 8 | 
                        Install clients 
                            on test hardware - AIX, SUN, Linux, Windows, (Mainframe?) 
                            | 
                        15 days | 
                        Fri 10/4/02 | 
                        Thu 10/24/02 | 
                        7 | 
                        Bob,Eric,Klara,Dale | 
                      
                      
                        | 9 | 
                        Install SNMP 
                            monitors (for example: http://net-snmp.sourceforge.net)  | 
                        15 days | 
                        Fri 10/4/02 | 
                        Thu 10/24/02 | 
                        7 | 
                        Bob,Eric,Klara,Paul | 
                      
                      
                        | 10 | 
                        Compare SNMP 
                            and OpenView monitors  | 
                        7.5 days | 
                        Fri 10/25/02 | 
                        Tue 11/5/02 | 
                        9 | 
                        Bob,Eric,Klara,Dale | 
                      
                      
                        | 11 | 
                        Security  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                        Kim,Paul,Bob,Eric,Klara | 
                      
                      
                        | 12 | 
                        Evaluate BEA 
                            Welogic App Server SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Klara,Pam Stagl,Mike Ates | 
                      
                      
                        | 13 | 
                        Evaluate BEA 
                            Welogic Web Server SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Klara,Pam Stagl,Mike Ates | 
                      
                      
                        | 14 | 
                        Evaluate BEA 
                            Tuxedo SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Klara ?? | 
                      
                      
                        | 15 | 
                        EvalutatePeopleSoft 
                            SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Klara ?? | 
                      
                      
                        | 16 | 
                        Evaluate ORACLE 
                            SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Dave Rhude | 
                      
                      
                        | 17 | 
                        Evaluate iPlanet 
                            SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Klara ?? | 
                      
                      
                        | 18 | 
                        Evaluate Portal 
                            Infranet SPI  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Paul,Klara | 
                      
                      
                        | 19 | 
                        Evaluate Internet 
                            services  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Mike Ates,Pam Stagl,Klara | 
                      
                      
                        | 20 | 
                        Mainfarme monitoring  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Steve Wilcox | 
                      
                      
                        | 21 | 
                        Telecom monitoring  | 
                        20 days | 
                        Thu 10/31/02 | 
                        Wed 11/27/02 | 
                          | 
                        Klara,Catie Isenberg,Terri Kopish | 
                      
                      
                        | 22 | 
                        Map building 
                            and event correlation  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                        Paul,Bill,Scott | 
                      
                      
                        | 23 | 
                        Design implementation 
                            method for server hardware monitoring with timeline  | 
                        15 days | 
                        Mon 12/2/02 | 
                        Fri 12/20/02 | 
                        22 | 
                        everyone | 
                      
                      
                        | 24 | 
                        Service monitoring 
                            - correlating events to provide a single service view. 
                            Evaluate use of SPIs  | 
                        61 days | 
                        Mon 9/30/02 | 
                        Mon 12/23/02 | 
                          | 
                          | 
                      
                      
                        | 25 | 
                        Design monitoring 
                            solution for critical Applications  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 26 | 
                        Hospital  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 27 | 
                        HAN/NEDSS  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 28 | 
                        911 Database 
                            and data transfer  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 29 | 
                        DoIT Telemanagement  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 30 | 
                        DoIT Directory 
                            and Messaging  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 31 | 
                        ISIS  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 32 | 
                        MUM  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 33 | 
                        WiscMail  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 34 | 
                        SFS  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 35 | 
                        FASTAR  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 36 | 
                        WEBCT  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 37 | 
                        Library  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 38 | 
                        Housing  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 39 | 
                        APBS  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 40 | 
                        HR  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 41 | 
                        ESIS  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 42 | 
                        Legacy Accounting  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 43 | 
                        Tax Reporting  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 44 | 
                        Purchase Order 
                            Print  | 
                        20 days | 
                        Wed 11/20/02 | 
                        Tue 12/17/02 | 
                          | 
                          | 
                      
                      
                        | 45 | 
                        Map building 
                            and event correlation  | 
                        35 days | 
                        Thu 10/31/02 | 
                        Wed 12/18/02 | 
                          | 
                          | 
                      
                      
                        | 46 | 
                        Security  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 47 | 
                        Design timeline 
                            for implementation service by service addressing mission 
                            critical services first. Mission critical services 
                            have been identified in the DRP document. (summarize 
                            individual documents)  | 
                        5 days | 
                        Tue 12/17/02 | 
                        Mon 12/23/02 | 
                          | 
                          | 
                      
                      
                        | 48 | 
                        Network  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 49 | 
                        Use test network 
                            (21st Ctry network) to test device monitoring  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 50 | 
                        Use WiscNET 
                            to test autodiscovery  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 51 | 
                        Map building 
                            and event correlation  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 52 | 
                        Security  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 53 | 
                        Design timeline 
                            for implementation of monitoring both the new platfrom 
                            network and the 21st Ctry network  | 
                        45 days | 
                        Mon 9/30/02 | 
                        Fri 11/29/02 | 
                          | 
                          | 
                      
                      
                        | 54 | 
                        Nontechnical  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 55 | 
                        QoS  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 56 | 
                        Procedures 
                            for problem resolution  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 57 | 
                        Problem ownership  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 58 | 
                        What does HD 
                            do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 59 | 
                        What does DCO 
                            do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 60 | 
                        What does NET 
                            do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 61 | 
                        What do SEO 
                            technologists do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 62 | 
                        What does NET 
                            do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 63 | 
                        What do ADI 
                            do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 64 | 
                        What does EIS 
                            do?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 65 | 
                        Ongoing role 
                            for Security group?  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 66 | 
                        Bringing up 
                            additional/new devices/services  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 67 | 
                        Intergration 
                            with Clarify  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          | 
                      
                      
                        | 68 | 
                        Hosting of 
                            external customers  | 
                        50 days | 
                        Mon 9/30/02 | 
                        Fri 12/6/02 | 
                          | 
                          |