Managing Items

This task shows you how to assign or un-assign items to process activities.

You must assign items to compute an analysis:

  • One or several Positioning System or Datum Reference Frame to all activities. See Creating Positioning System.
  • Fastening only to a Fastening or Already Done Fastening activity. See Creating Fastening.
  • Annotation Bag or Tolerancing capture to all activities. See Creating Annotation Bag.
    You can assign one or more Annotation Bag/Tolerancing capture but only one will be take into account with the following rule:
    • the first Annotation Bag then the first Tolerancing capture in the item's list.
    • The first Annotation Bag then the first Tolerancing capture in the list is taken into account.
    • The first item in the list is taken into account.
  • A Contact to any kind of activity (Positioning, Fastening or Release). See Creating a Contact.
    • If a Contact is already linked to a Fastening Element through a Contact Link, you must first delete this Contact Link, and then assign the Contact to the Fastening Element.
    • If a Contact is directly assigned to an activity, it is not possible to generate a Contact Link, even if the option Link Creation Mode is set to Automatic.

You may assign:

  • An item to several activities.
  • Several items to an activity.

You may un-assign:

  • Several items from an activity.
Open the BasicTaaProcess2.CATProcess document.
  1. Click Item Assignment

  1. Select Positioning System.6 and TolerancingBag.1 items.

  1. Select the Release.3 activity.

Positioning System.6 and TolerancingBag.1 are assigned to the Release.3 activity.

  1. Click the Unassign an item icon:

  1. Select the Release.3 activity.

The Items dialog box appears.

  1. Select TolerancingBag.1 item in the dialog box.

  1. Click Unassign.