ITEM: K8028L
DCE/ENCINA: "ppcadmin query stats" enc-ppc-0007: allocation failure
Question:
AIX 3.2.5
Encina for AIX 1.1.2
CICS/6000 vers. 1.1.0
The customer is running CICS/6000. He is using the Encina PPC
Gateway to talk to CICS on a mainframe.
When running the command "ppcadmin query stats" the customer
gets the following error message:
enc-ppc-0007: allocation failure, transaction scheduler failure
Response:
This message will occur in any of the following situations :
- DCE is down
- The command is directed at a PPC Gateway server that does not
exist (ENCINA_GWY_SERVER not correctly set)
- Possible stale DCE rpc endpoints
or
- The PPC Gateway server is not up
Support Line: DCE/ENCINA: "ppcadmin query stats" enc-ppc-0007: allocation failure ITEM: K8028L
Dated: July 1994 Category: N/A